Scope of Work
Wayne Brothers supported a critical equipment demolition requiring the lift and transport of a 60,000-pound oversized component. The scope included pre-lift planning, onsite coordination, and real-time logistics support to ensure the crane pick proceeded safely and on schedule.
Unique Challenges
With the crane already en route, a last-minute hauler cancellation threatened to derail the schedule. Our team quickly mobilized, calling in logistics specialists from our sister company Preferred Supply to evaluate the load and determine a trailer solution. Permitting, load configuration, and route clearance were coordinated within 24 hours—a true example of agility under pressure.
Notable Statistics
60,000
							
							Pounds						2
							
							Hour response Time from PCS logistics team						24
							
							Hours from issue discovery to permit approval						1
							
							Fully recovered schedule						 
								 
								