Scope of Work
Wayne Brothers was engaged to deliver critical site development and utility installation for a data center project in North Carolina. Our team prepared the building pad to exact elevations. Utility installations included domestic water service, fire line water systems, a complete sanitary sewer network, and a stormwater drainage system with inlets and piping. All executed to support the fast-paced demands of data center construction.
Unique Challenges
This project required quick problem-solving to maintain the schedule. When reinforced concrete pipe (RCP) was unavailable, our team kept the schedule moving by installing HDPE pipe as an approved alternative. Utility crossings required close coordination with the duct bank excavation, and our crews ensured accuracy by pre-installing sleeves in areas where pipe was not yet available, then returning later to complete the work once materials arrived. Several utility crossings were delivered in phases to minimize conflicts, reduce downtime, and keep other trades moving forward without interruption.