Client: Kajima Building Group
Status: Complete
Location: Mooresville, NC
Scope: Turnkey Concrete
Project Manager: John Vaughan
Superintendent: Todd Ashworth

WBI was excited to work for Kajima Building Group and NGK Ceramics of Mooresville, NC. WBI completed their contract of two separate building expansions. The concrete scope of work for the first expansion, the Kiln Building was completed mid October. The second phase, the forming building started in January 2013 after the Mazeppa road was relocated. Thank you to our Superintendent Todd Ashworth, Project Engineer Wesley Douglas, Foreman Terry Davis, Foreman Roy Reaves and the NGK team for a job well done with the aggressive schedule and difficult job site conditions.

Even with an aggressive schedule and logistical challenges, the Kiln Building and foundations for the Forming Building turned out great! Thanks goes out to Kajima Building & Design Group for their continued support throughout this project. Thanks to all WBI personnel for making this project a success.